Build a Villa (Construction Permit)
Drawings to dig day.
4
Steps, one application
AED 4700
Total fees
~16 days
Est. completion
vs 29 days one by one
2
Documents, upload once
About this service
Building on your plot needs a consultant, municipality approval and utility clearances. The permit path is sequenced here.
What happens, step by step
-
1
Appoint Consultant & Drawings
Licensed Engineering Consultant
Appoint a consultant to prepare stamped drawings.
-
2
Building Permit Application
Dubai Municipality
Submit drawings and plot documents for approval.
-
3
Utility NOCs
DEWA & Service Authorities
Clearances confirming no cables or pipes cross the dig.
-
4
Permit Issuance
Dubai Municipality
The building permit is issued and work can start.
Documents you'll need
-
Title Deed
Proof of plot ownership -
Architectural Drawings
Stamped by your consultant